Friday, 08 January 2010 13:21 |
|
Page 1 of 3 The following answers to frequently asked questions address the role of the U.S. Department of Energy (DOE) Weatherization Assistance Program funding to the states under the American Recovery and Reinvestment Act of 2009. You can learn more about the 2009 Recovery Act on the DOE Office of Energy Efficiency and Renewable Energy (EERE) Web site.
- Monitoring and Reporting
- Training
- Home Audits and Technical Support
- Federal Funding, State and Local Spending
- Best Practices
- Historical Preservation
- Weatherization Program Background
- Impact of the 2009 Recovery Act on Weatherization
Monitoring and Reporting
-
What are DOE Recovery Act reporting requirements?
Recovery act reporting requirements fall into two broad categories:
- OMB reporting requirements
- Program-specific DOE reporting requirements
OMB reporting requirements for the quarter ending on September 30 have been finalized. These reports are due to FederalReporting.gov on October 10, 2009. A full description of these requirements is published on the Recipient Reporting Information section of the Recovery.gov Web site. DOE will also issue additional FAQs for recipients on its Energy Recovery Web site and has set up a hotline to answer any additional questions: 1-888-DOE-RCVY (1-888-363-7289).
-
What reporting items and metrics are States and sub-recipients required to submit?
For OMB required reporting into FederalReporting.gov, recipients will input 31 data elements. These elements comprise primarily organizational, financial and jobs related information, and do not include performance metrics, which will be covered in program specific reporting. Some key data elements include:
- Amount of award
- Total amount of Recovery Act expenditure
- Sub-awards:
- Basic data elements for any sub-awards over $25,000
- Total number and amount of sub-awards
- Vendors
- Basic data elements for any purchases more than $25,000
- Total number and amount of payments to vendors less than $25,000
- Number and description of jobs created or retained (by both prime and sub-recipients)
- Primary place of performance
- Top five highly compensated officers
For a complete list of all data elements, please see Recipient Reporting Information on the Recovery.gov Web site.
-
Will DOE require new performance metrics based on energy savings, energy efficiency, or other outcomes of the Weatherization Assistance Program (WAP)?
Not at this time. DOE is in the process of conducting a new national evaluation of the WAP. In addition to the traditional metrics, this effort will expand to include emphasis on bill reductions. In the near future, DOE will focus more on non-energy benefits such as carbon reduction and health and safety impacts.
-
Are States and/or sub-recipients required to conduct monthly monitoring?
The reporting requirements are currently being modified to require monthly reporting for Recovery Act funded activities and will be made available to the network upon completion.
-
How should States determine energy savings?
DOE is developing a simplified methodology that multiplies the number of weatherized homes by standardized state-by-state energy savings (supplied by DOE) which will provide quarterly savings information.
-
How are "jobs created" measured?
There are two broad categories of recipients: recipients of "financial assistance," including grants, loans, cooperative agreements; and direct Federal contractors. Recipients of financial assistance are subject to the full OMB guidance on jobs reporting and will report jobs created or retained by both the grantee and any sub-grantees.
Direct Federal contractors are governed by the FAR (52.204-11) and are not required to report sub-contractor job creation.
Both recipients of financial assistance and contractors should report direct jobs created and retained using a standard calculation, translating both full- and part-time employees into "full-time equivalents," (FTEs), using the following formula:
Cumulative total hours worked by all employees in the quarter Cumulative total hours in a full-time schedule
Examples: A "half time employee" = 0.5 FTE. Equally, a full-time employee who is only 50% funded from Recovery Act funds = 0.5 FTE. An employee who works overtime (time and a half) = 1.5 FTE.
Recipients should be careful to report only direct jobs. That is, any job that is directly funded by the Recovery Act on the grantee or sub-grantee level. Indirect jobs—those that are not directly funded by Recovery Act funds or those that are created by a material supplier—are not reported into FederalReporting.gov.
-
How do we calculate job counts for contractors on pay-for-performance systems (specifically, lead generation contactors)?
Grants and Loans If the original source of the funding is financial assistance—grant, loan, or collective agreement—the prime recipient will estimate job creation for the sub-contractor. In this case, the recipient will need to convert the piece-rate or pay-for-performance system into an FTE equivalent to the best of their ability for reporting purposes. The recipient can use the industry-specific standard full-time schedule for the denominator in the FTE equation.
Cumulative total hours worked by all employees in the quarter Cumulative total hours in a full-time schedule
For the purposes of an FTE calculation the "wage rate" is not relevant, so the recipient should calculate the jobs count based on estimated hours worked.
Contracts If the original source of Federal funding is a contract, the recipient will not report the sub-contractor job creation numbers.
-
Are administrative expenses reportable to Recovery.gov?
Administrative expenses are reported in the WAP consistent with the associated activities under the DOE grant. DOE will compile the costs and make any necessary reporting to Recovery.gov.
-
With regards to the reporting function, is it better to centralize reporting with States or allow sub-recipients to handle their own reporting to DOE?
For OMB reporting requirements, the prime recipients (e.g. States) have the option of delegating some reporting requirements to their sub-recipients or reporting themselves. DOE does not have a preference on this issue, but urges prime recipients to consider both the details of a data collection mechanism, the administrative burden and which method would elicit the most accurate data. In either case, the prime recipient is responsible for clearly communicating the information and reporting needs to its sub-recipients.
It is also important to note that recipients of grants, loans and cooperative agreements cannot delegate the jobs reporting requirement to sub-recipients. They must collect that information from the sub-awardees, and they are responsible for entering that data element as an aggregate number of jobs created/retained by both the recipient and the sub-recipient.
-
What's a reasonable frequency of field inspections for the WAP?
DOE is currently amending the monitoring and oversight requirements under the Recovery Act. Generally, 5% inspections of completed units is recommended, however, this figure is likely to increase under the Recovery Act.
-
Are States advised to supplement their field monitoring staff with outside evaluators who can measure impacts, benefits, and cost-effectiveness of grantees' energy programs?
For certain States, Recovery Act funding represents a 25-fold increase in funding. Ramping up the States' capability to adequately supplement additional staffing will be critical in providing the necessary oversight of the WAP with Recovery Act funds. Using outside evaluators could help mitigate this shortfall in staffing.
-
How can States best reconcile the historical metrics by which State agencies have gauged the progress of their programs with the added metrics (i.e. job creation/retention) from the Recovery Act?
DOE is currently amending the WinSAGA system to accommodate the new reporting requirements. Grantees will be notified when these updates have occurred, including how to report jobs created.
-
Does DOE require States to report any additional data not currently defined in the OMB or Recovery Act terms and conditions?
No. Not at this time.
Training
-
Will DOE provide guidance on required training curriculum?
Yes. DOE is developing a comprehensive training and technical assistance plan which will address curriculum as well as many other related issues. This plan is expected to be released soon.
Home Audits and Technical Support
-
In the event that a State or sub-recipient requires additional technical assistance for its weatherization program, what resources are available?
There is a myriad of technical assistance available within the weatherization network. You should contact you State Weatherization Program Manager to discuss what is available in your particular State. Likewise, you can check the Weatherization Assistance Program Technical Assistance Center (WAPTAC) to see what is available nationally as well as what other States are doing.
-
Are there any recommended methods and technologies States and/or sub-recipients should use?
There is a myriad of technical assistance available within the weatherization network. You should contact you State Weatherization Program Manager to discuss what is available in your particular State. Likewise, you can check with WAPTAC Web site to see what is available nationally as well as what other States are doing.
-
What criteria determine which homes will be weatherized?
DOE suggests that local agencies and states determine eligibility based on poverty level, elderly in poverty, disabled, fuel costing. Local agencies should determine whether a particular unit is deemed to be a "good candidate home" for weatherization services. An assessment of whether the home needs any type of rehabilitation work or is free of major health and safety concerns can eliminate many units until they have been referred to the appropriate agency to have these major deficiencies corrected prior to weatherization.
-
Does DOE require States to use infrared technology in dwelling assessments?
No. DOE does not impose mandates on equipment. However, infrared cameras are an effective auditing tool that the grantees may choose to purchase for insulation purposes.
-
Are States encouraged to use new and innovative weatherization technologies or should they utilize more conventional measures?
No. DOE does not impose mandates on equipment.
-
Is guidance available for additional approved weatherization installation measures?
Weatherization measures will differ for each unit based on various factors including climate, existing materials, and cost. But the following measures are approved as long as the savings-to-investment ratio is 1.0 or higher:
- Insulation
- Air Sealing
- Windows
- Heating
- Water Heaters
- Air Conditioning and Warm Climate Weatherization Measures
- Electrical Appliances and Weatherization Base Load Measures
Read more about weatherization technologies on the WAP Web site.
If innovative technologies are available and meet the cost effective test, then grantees can request that DOE review and approve the technology for use in the field. The new technology must be used in the field for DOE to consider it as an allowable measure.
If there are additional measures that are not specified by DOE that your agency would like to utilize, please contact your State weatherization program liaison to seek approval from DOE.
-
Must "designated agencies" be used to do the work for the WAP? Can agencies beyond those listed in an application be used?
You cannot use agencies beyond the one you listed in your application per Code of Federal Regulations Title 10 Part 440.14. However, DOE encourages the use of new and innovative technologies that are designed to improve program performance.
-
Must legal status be confirmed for all weatherization assistance recipients, specifically those residing in multi-unit dwellings?
The U.S. Department of Health and Human Services (HHS) issued Information Memorandum LIHEAP-IM-98-25 dated August 6, 1998, outlining procedures for LIHEAP and WAP grantees serving non-qualified aliens to implement new status verification requirements. This memorandum is based on a proposed rule issued by the Department of Justice (DOJ) on August 4, 1998. The Welfare Reform Act is a complex issue and there is some confusion on the specific application of this part of the Act. To insure WAP continuity between LIHEAP and Weatherization for the many sub-grantees operating both programs, the WAP will follow the interpretation as adopted by HHS.
The primary area of confusion resides in the types of local agencies that are exempt/nonexempt from "status verification requirements." Local agencies that are both charitable and non-profit, which comprise about three-quarters of the local agency network, would be exempt.
However, those agencies which are designated as local government agencies operating the WAP would not be exempt and, therefore, must conduct "status verification." Under the DOJ ruling, Grantees subject to this ruling have two years to fully implement this procedure after the publication date of the final rule. As of this date, the final rule has not been issued.
-
Is blower door testing required for multi-unit dwellings?
No. It is not required, but it may be recommended. Some multi-unit dwellings—generally units that are one to four floors or garden style—function as a single-family unit. Therefore they would benefit from a blower door air leakage test. For larger multi-family buildings, a multi-family focused audit procedure (such as EQ-UIP) would be best.
-
If a blower door diagnostic of a home passes initial inspection, but the home is in obvious need of weatherization services (via duct blaster or infrared inspection), are contractors still authorized to perform work?
If a client qualifies for WAP funds and does not need air sealing or insulation but needs additional measures, then that unit should be completed with the appropriate measures. The cost of the completion would then be lower.
-
Do blower door tests have to be performed twice per house, once when the improvements are being made and once by the quality assurance team?
A diagnostic energy audit is required on all DOE units; this audit includes blower door testing. The post inspection/quality control is the same as the diagnostic audit; it just ensures that the installations were completed effectively. It is also a best practice and DOE recommendation that blower door tests are completed as the measures are being installed, especially when air sealing.
|
|